GSoC 2017 - Timeline Navigation - Weekly Report #11

Posted 6 years ago

Hey everyone!

This is my eleventh weekly report for my GSoC project. This will include all the work from the past week. It includes my key accomplishments up to this point, the tasks that have given me trouble, and my plan for the next week.

Key accomplishments

-Pull Request

-Finally a PR has been initiated. Currently, I am cleaning up a couple last minute bugs and making my code fit within the guidelines.

-Tricky bugs

-Multiple bugs were found dealing with text tools and drum tools and the piano keyboard. Figuring these out took much longer than expected as I didn't quite understand what Qt was doing.

Key tasks that stalled

No tasks stalled

Tasks in the upcoming week

-Finish the pull request and fix the newfound bugs

-Check my personal Issue tracker

There are some smaller tasks next week that will happen after the PR. These are listed on my personal issue tracker. You don't have to go look at it, but if you do, feel free to state your opinion on some of them! https://github.com/JoshuaBonn1/MuseScore/issues

-Begin asking for opinions on graphics and changing over to the general palette for colors

I will be posting a main graphics discussion post to the forums to figure out how it should look. See: https://musescore.org/en/user/1190941/blog/2017/08/05/gsoc-2017-timelin… for a picture of the current timeline

Thanks for reading!

Joshua Bonn

GitHub: https://github.com/JoshuaBonn1

(Current branch is https://github.com/JoshuaBonn1/MuseScore/tree/8-timeline-class )

IRC nick: JoshuaBonn1